I just find it mysterious that the original contract was cancelled in 2002. So it would seem to me that PWGSC, which was overseeing the tendering, would be on high alert, and yet the second contract had flawed information.
You mentioned here--and I'm just wondering if I could get a sense of it from whoever was in charge of this audit--that a number of times information was requested. Do you know exactly how many times the other bidders requested additional information and were rebuffed?