Let's sort of separate two things here--the overall cost of the project versus the cost of the trains. The trains are really the small part of the package. The trains represent, I would say, maybe 10% of the cost of a project. The big cost is land acquisition and construction, and building all the bridges to separate the road traffic. Just that aspect is going to be 65% of the cost of the project, maybe more.